Corrosion Control in the Eagle Ford Shale

Corrosion control is always a factor in oilfield work.  Above-ground tanks, pipelines, and all manners of equipment suffer from corrosion, both internal and external in nature.  The farther south and west one moves across the Eagle Ford play, the more two interesting physical facts come to dominate external corrosion control needs. Maverick, Dimmit, Zavala, Webb, La Salle, McMullen, Frio, Atascosa, Live Oak and Bee Counties have shallow soils which often contain large concentrations of chloride ion.  This comes from salt deposited when ancient ocean shorelines ranged across the region.  High chloride ion content causes aggressive corrosion rates on unprotected steel.  Just as importantly, the sodium and chloride ions, often found with other ions as well, cause the soil’s electrical resistivity to be very low.  The low electrical resistance means high corrosion current flows, which again accelerates attack on unprotected steel.  Pipelines are buried in this soil.  Tanks are set on it.

Even in the other counties in the play, external corrosion is a big factor.  Those soils are often clayey loams with varying amounts of gypsum and other water-soluble minerals.  So corrosion potential is high, no matter where you’re working.

Best Practices for Corrosion Control

Corrosion protection for these facilities should always include a combination of good coatings, good installation and inspection practices, and well-designed cathodic protection (CP) systems.  Here are some pointers for the southwesterly “half” of the Eagle Ford:

  • If constructing bulk above-ground storage tanks (ASTs), put a coating on the bottom plate before field welding begins.  This coating will give partial protection to the finished external bottom of tank.  This reduces the amount of protective electrical current needed.  It lowers capital costs for the CP system, AND can greatly reduce a monthly electric bill;
  • If high-voltage AC power lines are nearby, avoid setting up pipeline rights-of-way in “close parallel” to the AC lines!  With the low soil resistivities, high chloride levels, and good coatings, the AC-induced corrosion rates are EXTREMELY HIGH!  (An article about this risk will come soon.)
  • Holiday detection is even more important for coatings inspection on pipelines, tanks, and, really, on any paint job where the metal will be in soil or water contact.  Remember, too, that water gets everywhere, sooner or later;
  • Coat the bottom of every steel vessel before it is set – not just a paint, but a better-quality and thicker coating!  Dehydrator units, separators, bulk tanks all may be set on crushed rock or caliche, but the chloride ion will move to the metal – just by diffusion – and attack it over time.

These observations and recommendations are based on experience, not on “ivory tower” theorizing.

Basics of Corrosion Science

For those not so familiar with corrosion science, here are a few points to keep in mind:

  1. If we just talk about steel, it is not a “naturally occurring” material.  Iron ore is dug up, then combined in very hot furnaces with coke and other alloying metals.  The resulting steel is then cooled, shaped, and so on;
  2. A lot of new energy is added in the metal-making process.  As soon as this metal is put into the environment, Mother Nature’s electrochemical processes go to work.  Their goal is to turn steel back into iron ore – rust!  The reason?  All that energy put into the making of steel is now available to be removed.  One physical law is that everything, sooner or later, will be “taken back” to its lowest stable energy content;
  3. To prevent or slow down that rusting process, every piece of steel should be coated, maybe even inside as well as outside.  No water, either liquid or vapor, should be allowed to contact it.  Water is the major "rusting agent" around, even if just a vapor or a dewfall.  And there are plenty of other chemicals which may drive the corrosion process, chloride ion being one;
  4. Finally, in addition to the coatings, cathodic protection should be applied.  Coatings by themselves are not good enough, because there are always defects or holes in them.  And the cathodic protection should be sized to give protection for as many years as you want the structure to do its job.

Mr. Chapman is one of many professionals who will be contributing to EagleFordShale.com. If you have professional experience in the Eagle Ford and would like to be considered as a contributor, please Contact Us about guest blogging.

Laredo Job Fair January 13, 2012

Don't forget the Laredo Eagle Ford Job Fair on Friday, January 13th, starting at 9 am at the Laredo Energy Arena (6700 Arena Blvd, Laredo, Texas, 78041). The city along with area partners are hosting the event that will have more than 110 companies participating. Come early. Blasita Lopez, of the Laredo Convention and Visitor's Bureau, expects there will be more than 2,000 attendees at the event. More than 40 of the companies will be taking applications and interviewing candidates, while the rest will have their products and services on display. Workforce solutions will also be on site to help build resumes and submit applications.

Eagle Ford companies will be filling open positions for administrative, labor, driving, engineering, and even executive positions. Have your resume up to date and be prepared to interview.

Don't forget that you can search and add listings for open positions at our Eagle Ford Jobs page right now.

Registered vendors include:

HalliburtonAssc. Laredo Forwarding Agents

Holt CATCarrizo Oil & Gas

Bassler Energy ServicesSanjel USA

Key Energy ServicesJW Human Resources

WilsonKilliam Oil Co.

UNI-TRADE ForwardingLewis Energy Group

Just EnergyPrimerica Financial Services

Western Summit Contractors, Inc.Industrial Gear and Solutions

ManpowerSun Coast Resources

Spartan Oil Field ServicesWorld Ventures

Laredo Energy ArenaThomas Petroleum

HLI Energy ServicesSafety Management Systems

Pilot Flying J TransportationExterran

Mainline ServicesChesapeake Energy

Harlee's Key ServiceHill Country Well Services

South Texas Auto RebuildersCOMEX (PEMEX)

Alarm Security GroupFirst Convenience Bank

Staff Force Personnel ServicesSOS Staffing

Nabors Well ServicesTravel Centers of America

Terracon ConsultantsTSI

Martin InstrumentPatterson-UTI Drilling

 

 

GeoResources Sells Atascosa Acres - Focusing in Fayette and Gonzales

GeoResource sold 1,800 acres in Atascosa County in late 2011 and plans to focus its efforts in southwest Fayette County and northeast Gonzales County. The company has drilled seven wells to date and has two rigs that will continue Eagle Ford drilling. A recent well in Gonzales County reached a total measured depth of 14,700 ft in 24 days. The company's current well costs run $8.5-9 million and batch completions will be used to help drive costs down further.  

GeoResources is also completing a seismic survey that will help the company identify drilling locations int the Austin Chalk, Buda, Edwards, Eagle Ford, and Georgetown formations.

Operated Eagle Ford Area Highlights

  • 4 gross wells spud in fourth quarter 2011
  • 4 gross wells currently waiting on completion
  • 2 wells currently drilling (1 spud in late December 2011 and 1 in early January 2012)
  • 3 gross wells currently producing
  • All 3 completed in second and third quarters of 2011
  • 48% average working interest
  • Average first 30 day production rate of 409 boe/d
  • 20 to 25 gross wells planned to spud in 2012

 

Talisman Energy Sets 2012 Eagle Ford Shale Budget - $500 Million

Talisman Energy expects to spend more than US$4 billion in 2012 and spending in the liquids-rich Eagle Ford Shale play will increase from $350 million in 2011 to $500 million. The company operates 10 Eagle Ford drilling rigs currently and plans to ramp up to 14 by the end of 2012. The increase in spending in South Texas comes on the back of a decrease in spending across North America. Talisman will spend $1.8 billion in North America in 2012 versus $2.2 billion in 2011. The cut is largely the result of less activity in dry gas plays that are challenged in the current $3/mmbtu natural gas environment. The company expressed a belief that natural gas prices will remain at depressed prices for some time.

Talisman's North America portfolio is centered in the Eagle Ford, Marcellus, and Canadian shale plays. Talisman acts as the operator for the joint venture with Statoil where the companies jointly own acreage covering much of the liquids-condensate window in the play.

"We expect to spend approximately $4 billion in cash capital expenditures this year. We are reducing capital spending in dry gas plays in North America, which accounts for the majority of the decrease over 2011. Underpinning this is a belief that North American gas prices will remain low for some time; we have also assumed a relatively conservative oil price forecast.

Read more at talisman-energy.com